South Wales Main Line Electrification – Newport Area
Original
Schedule Key Dates
On the 23rd July 2009 the then Labour Government stated that,
"work will begin immediately on the electrification of the Great Western
Main Line between London, Reading, Oxford, Newbury, Bristol, Cardiff and
Swansea, to be completed within eight years" (2016/2017).
After the 2010 UK general election in May 2010, the coalition
Conservative/Liberal Democrat alliance placed all major government capital
expenditure, including the Great Western electrification scheme on hold pending
a return-on-investment review. In November 2010, Transport Secretary Philip
Hammond gave the go-ahead for the lines from Oxford via Didcot
to London and Newbury to London to be electrified in the next six years.
Extension from Didcot to Swindon, Bath, Bristol and to South Wales would be dependent on a further
assessment due in 2011 of the costs and implementation requirements of the
Intercity Express Programme.
On 1 March 2011, transport secretary Philip Hammond announced
that rail electrification from Didcot Parkway to
Bristol Temple Meads and Cardiff Central would go ahead. The section linking
Bristol Parkway and Bristol Temple Meads would also be electrified.
In July 2012, the UK Government announced that the final portion
of the Great Western from Cardiff to Swansea would be electrified.
So when will the wires appear?
There have been a number of timescales reported in various
publications: Here are two reported schedules:
1) Initial plan is that the GWML would be electrified to Bristol
by 2016, and extended to Cardiff by 2017.
2) The plan had been to
get wires to Oxford, Newbury and Bristol Parkway by 2016, to Bath and Bristol
Temple Meads by 2017, and to Cardiff and Swansea by 2018
Bridge
and other Infra-Structure Works
As part of
our plan to electrify the South Wales Mainline, there have are a number of Key
Engineering Projects in the Newport area , mainly a number of bridgesthat will require modification as they are too low
to accommodate the overhead wires or need to be upgraded due to Safety issues.
The following
is a list of the known work with a reference to the document “Map of bridge works in Newport” released by Network Rail to communicate the tasks that were to
happen.
For
information the document relating to the adjoining area of Monmouthshire can be
found here
|
STATUS : 3rd Jan 2016 |
|
Not Started |
|
IN PROGRESS |
|
Completed |
|
NR Document Ref No |
Structure |
Planned works |
Proposed start date |
Proposed end date |
Additional information |
|
1 |
Reconstruction |
September 2015 |
May 2016 |
The bridge will be
closed to vehicles and pedestrians in November 2015 (and will remain closed
until Spring 2016). An appropriate diversion is in place for road traffic and
a temporary footbridge has been installed directly to the east of the bridge
to maintain access for pedestrians. |
|
|
2 |
Chepstow
Road Rail Bridge |
Minor
works |
February
2016 |
Spring
2016 |
|
|
River
Usk Bridge |
Electrification
Mast erection |
||||
|
3 |
Newport
Station Footbridge |
Demolition |
May
2016 |
May
2016 |
The
redundant footbridge will be removed. |
|
4 |
Bridge
Street Road Bridge |
Reconstruction |
Summer
2016 |
Late
2016 |
We
expect the road will be closed for approximately six months (exact dates TBC).
An appropriate diversion will be in place for road traffic and pedestrian
access will be diverted over the neighbouring Tunnel Terrace footbridge. |
|
5 |
Tunnel
Terrace Footbridge |
Reconstruction
/ Jacking |
TBC |
TBC |
|
|
6 |
Newport
Old Tunnel |
|
TBC |
TBC |
|
|
7 |
Reconstruction |
November 2015 |
May 2016 |
We expect the road
will remain open to traffic (and pedestrians) during the work but with single
lane traffic only and traffic calming measures in place. |
|
|
18 |
Demolition |
December 2014 |
December 2014 |
|
|
|
9 |
Maesglas Road Bridge |
Reconstruction |
Late
2016 |
2017 |
|
|
10 |
Reconstruction |
November 2015 |
April 2016 |
|
|
|
Reconstruction |
November 2012 |
April 2013 |
|
||
|
11 |
Maerdy Farm Road Bridge |
Reconstruction |
November 2015 |
April 2016 |
|
|
12 |
Hawse
Lane Road Bridge |
Reconstruction |
TBC |
TBC |
|
|
13 |
Summerway Road Bridge |
Reconstruction |
June
2016 |
Early
2017 |
|
|
14 |
Green
Lane / Heol Las Road Bridge |
Reconstruction |
Summer
2016 |
Spring
2017 |
|
Actual
Events Key Dates
This list the actual dates when key events both locally and
nationally occurred during the project.
|
Date |
Location |
Event |
|
1st & 3rd Jan 2016 |
Partd for new Bridge Deck lifted into
position |
|
|
26th Dec 2015 |
New Pier Supports lifed into place |
|
|
25th Dec 2015 |
Demolished |
|
|
25th/26th Dec 2015 |
Demolished |
|
|
25th/26th Dec 2015 |
Westbound Bridge Deck removed
|
|
|
Dec 2015 |
Bridge Closed |
|
|
1st Dec 2015 |
Bridge Closed to pedestrians. Pedestrian access via temporary
footbridge |
|
|
1st Nov 2015 |
Westbound Lane closed, Single file traffic on eastbound side |
|
|
1st Nov 2015 |
Bridge Closed to vehicles |
|
|
12th March 2015 |
First Hitachi IEP train arrives in UK from Japan |
|
|
25th Dec 2014 |
Removal of old Alexander Dock Railway Bridge |
|
|
22nd Apr 2013 |
Reopened to traffic |
|
|
12th Nov 2012 |
Closed to all traffic |
Images
of Work Progress
The following shows images of the changes and includes before and
after images and Work in Progress Images. You can click on the following links
to go to the relevant sections:
|
Some images of Somerton Road Bridge
when in use in early 2015. |
||||
|
|
||||
|
|
||||
|
These images were taken on 13th
December 2015, following closure and prior to demolition and are taken from
the temporary footbridge diversion that was in place. What is noticeable is
where work has been done on the Northern and Centre supports on the parts
that are to remain while the site is prepared for the construction of a new
southern supporting pier. |
||||
|
|
||||
|
|
||||
|
On the 24th December 2015 it can be
seen that the new Southern support is completed. This was last view of
everything as it was prior to work commencing on the site at 23:00. All of
which had to be done in a 56 Hour window |
||||
|
|
||||
|
|
||||
|
At around 12:00 on the 25th - 13
Hours into the work the following has been undertaken. ·
Protective
track cover in place ·
Road surface
removed from bridge ·
Removal of
embankment on approach to Northern side of Bridge |
||||
|
|
||||
|
|
||||
|
At around 18:00 on the 25th - 19
Hours into the work the following has been completed since earlier. ·
Northern Bridge
removed ·
Northern
Approach Embankment removed ·
Northern Pier
reduced to new height |
||||
|
|
||||
|
|
||||
|
At 09:00 on the 26th - 34 Hours into
the work the following has been undertaken since the previous evening. ·
Southern Bridge
removed ·
Southern
Approach embankment cut back ·
Centre Pier
reduced in height ·
First section of
new support in place on Northern Pier ·
Track
protective cover being removed |
||||
|
|
||||
|
|
||||
|
At 17:00 on the 26th - 42 Hours into
the work the following has been undertaken since earlier that day. ·
Protective
track cover completely removed ·
New Northern pier
supports all in place ·
Preparation for
placement of new supports on Centre Pier |
||||
|
|
||||
|
|
||||
|
At 12:00 on the 27th and the line had
been opened on schedule and the following are seen. ·
New Centre Pier
Support in place ·
New Southern
Pier Support in place |
||||
|
|
||||
|
|
||||
|
On New Years
Eve (31st) the first cross members of the new bridge were lifted into place
during an eight hour
period. |
||||
|
|
||||
|
|
||||
|
On the night of the 2nd/3rd the remaining
sections of the bridge were lifted into place. The difference in height of
the old road way and new bridge are visible in the image below. |
||||
|
|
||||
|
|
||||
|
|
|
|
|
|
|
||||||
|
Some images of Cardiff Road Bridge taken
from Google street view showing what I looked like prior to work commencing. |
|
|||||
|
|
|
|||||
|
|
|
|||||
|
A view that shows the single file
traffic arrangement that was in place while the first the stage to replace
the Westbound carriageway bridge was undertaken. |
|
|||||
|
|
|
|||||
|
|
|
|||||
|
A view that shows the two styles of
bridge which makes up the bridge on Cardiff Road. A typical girder style
bridge on the left with a more traditional style stone bridge on the right. |
|
|||||
|
|
|
|||||
|
|
|
|||||
|
Three views that show the initial
construction work that was being undertaken to construct the supports for the
new bridge deck. These have been located behind the line of the original
bridges retaining walls. |
|
|||||
|
|
|
|||||
|
|
|
|||||
|
The following images show the
progress at around 12:00 on 25th December 13 hours into the
progress to remove the bridges. The stone bridge has been removed and
the work is currently on removing the steel bridge where the exposed steel girders
can be seen. |
|
|||||
|
|
|
|||||
|
|
|
|||||
|
By 09:00 on the 26th 34 – Hours into
the work both Bridges had been removed and work was underway to demolish and
remove completely the centre bridge support. |
|
|||||
|
|
|
|||||
|
|
|
|||||
|
|
|
|
|
|
|
|
||||||
|
||||||
|
Running Parallel to Cardiff Road
Railway Bridge was another Railway briadge that use
to carry the railway lines from the Western Valleys across the main line to
what was known as the Monmouthshire Bank railway sidings and provided access
to Newport Docks. This bridge had been redundant for at least 35 years and
was finally removed on Christmas Day (25th December) 2014. The
image below shows the removal in progress of the side members of the bridge |
|
|||||
|
|
|
|||||
|
|
|
|||||
|
|
|
|
|
|
|
|
||||||
|
||||||
|
Cuckoo Road Bridge is also known as
Pheasants Curve Bridge and is a dirt track road down to a farm and the sea wall
near the Mouth of the River Ebbw and has been very popular with Railway
photographers over the years. The image below was taken in early 2015 when a
steam special to Cardiff is seen passing underneath the bridge. |
|||||
|
||||||
|
||||||
|
|
|||||
|
|
|||||
|
The bridge was removed on Christmas
Day 25th December 2015. This is the view from the Lighthouse Road
Bridge on the 26th showing the gap where the bridge was. |
|||||
|
||||||
|
||||||
|
|
|||||
|
|
|||||
|
|
|
|
|
|
|
|
|
||||||
|
||||||
|
A view from Google Streetview of the bridge prior to replacement |
|||||
|
||||||
|
||||||
|
|
|||||
|
|
|||||
|
The replacement bridge seen from
Cuckoo Road Bridge looking towards Cardiff |
|||||
|
||||||
|
||||||
|
|
|||||
|
|
|||||
|
|
|
|
|
|
|
|
|
||||||
Page Updated:
3-Jan-2016